Projects

Roads & Bridges Projects

Project Descriptions

International Coastal Road Sector 7` and its Access.

Dual carriageway ( 3 lanes each direction ), its total length 14 km, contains 6 bridges, (3 flyover bridges and 3 surface bridges). the total length of bridges is 5.703 km , the longest being ( P1-P2 ) (1.5 km) which provides free interchange with Cairo - Alexandria Desert Highway , Bridge P5-P6 (588 m) and Bridge P12-P16 (650 m) , the surface bridges and Governorate Drain bridge , Almariotia Canal bridge and Almariotia Drain bridge.

Project Details

Client :Ministry of Housing, Utilities and New Urban Development - Central Org. for Construction - The Executive Org. for Construction of Middle Northern Coast.
Activity :Roads & Bridges
Location :Alexandria
Finished in :Feb., 2001