Project Descriptions
Water Supply Projects of 240 Deprived Villages at Beheira, Monufia and Gharbia Governorates .
The Project contains the following:
- G.R.P & H.D.P.E & U.P.V.C Water Pipelines with dia. 100 mm to 800 mm , 1450 km length.
- 2 no. Water Treatment Plants with capacity of 30 L/sec.
- Iron and Manganese removal Plants for artesian water wells (41 no.) with capacity from 25 to 125 L/sec.
- Elevated water tanks with capacity from 100 to 1000 m3 (48 tanks).
- 2 no. water pumping stations at Wadi el natroun & Abo ALmatameer
Project Details
Client :The National Org. for potable water & Sanitary Drainage |
Activity :Utilities |
Location :Beheira, Monufia and Gharbia Governorates . |
Started in :April, 2003 |